Abstract:  
           
          Although the birth of Precedence Diagramming Method (PDM) 
          is not as radiant as of CPM or PERT, but it is definitely the 
          prevailing scheduling technique of our times. This popularity 
          is due to its modeling flexibility over other techniques 
          and the easy-to-understand mathematical model behind the 
          technique. However, even this technique has its own limitations;
          modeling overlapping activities in a proper way seems 
          to be a never-ending debate. The reason of this can be found in 
          the fundamentals of PDM technique; the four precedence relationships 
          that form connections between the end-points of the 
          activities, 
          with constant production speed. These fundamentals of PDM 
          have their own consequences to scheduling practice; it is more 
          and more apparent among professionals that activity overlapping 
          in PDM cannot be modeled adequately. Different solutions 
          were proposed for solving this problem from the application of 
          negative lag, through the combination of SS and FF relations to 
          the fragmentation of activities. All these solutions have their 
          shortcomings. Probably the fragmentation technique has led 
          to the development of point-to-point type of relation that can 
          connect any arbitrary points of the dependent activities. The 
          objective of this paper is to analyze the pros and cons of different 
          solutions that are used for modeling overlapped activities, 
          then to show how newly defined point-to-point relations can be 
          used for this purpose. Algorithms that handles point-to-point 
          relations with minimal and maximal lags are also presented. 
          The main finding of the paper is that newly developed point-topoint 
          relations are better from theoretical and practical point
          of view than the solutions based on traditional precedence 
          relationships, but they still cannot provide theoretically perfect 
          solution for overlapping. This paper is the fully extended 
          version of a paper building on the results already presented on 
          the Creative Construction Conference [1]. 
          Keywords: Precedence Diagramming 
            Method, Activity 
            overlapping, Point-to-point 
            relations 
                       |